Boddington Gold Mine Tailings Storage Facility

Boddington Gold Mine

The project involved converting an existing water storage dam into the first stage of a 750,000m2 HDPE Lined Tailings Storage Facility.

Contract
Expansion Tailings Dam at Boddington Gold Mine

Client
Boddington Gold Mine

Consultant
Aker Kvaerner Australia

Contract Value

$30,017,968

Contract Start Date
October 2006

Contract Completion Date
May 2007

Description
The project involved converting an existing water storage dam into the first stage of a 750,000m2 HDPE Lined Tailings Storage Facility. The works had to be constructed during the summer months while controlling rainfall run-off and subsoil inflow.
 

  • 70ha of forest clearing.
  • 100ha of topsoil stripping.
  • Removal of 40,000m3 of rock.
  • Removal of 35,000m3 of unsuitable material.
  • 200,000m3 of cut to fill and reshaping
  • 300,000m3 of 300mm clay liner excavated and compacted.
  • 25km of 160dia Draincoil for underdrainage system.
  • 750,000m2 of 1.5mm HDPE liner.
  • 20km of 100mm Dia Branch Drain.

The Project Team comprised a Project Manager, 3 Engineers, 7 Supervisors, 2 Safety Advisors, 3 Site Clerks with an average workforce of 120 Ertech employees.